The Irish Self-Build Drawdown Checklist
What is commonly asked for at each stage of a self-build mortgage drawdown, who usually supplies it, and how to get it together 3–4 weeks before you need the money.
This is a preparation aid, not mortgage advice or lender approval. Requirements vary by lender and by case. Confirm what your lender needs with your lender, broker or solicitor.
3–4 weeks before each drawdown
Most drawdown stress comes from chasing one missing document at the last minute. Start early.
- 4 weeksAsk your lender or broker what this stage needsRequirements differ between lenders and cases. Get their list in writing and check it against this page.
- 3 weeksBook the stage inspection and certificateYour engineer or architect usually needs to visit site before signing a stage certificate. Their diary fills up.
- 2 weeksGather invoices, split into materials and labourAsk suppliers and trades for invoices covering this stage. Keep material and labour invoices separate.
- 1 weekTake clear site photos and check insurance datesPhotograph the finished work for this stage. Check your site insurance covers the dates you are building.
- SendSend one tidy packSend everything together to whoever handles your drawdown (often your broker or solicitor). Keep a copy.
The document people often forget
Site insurance with dates that cover this stage. Having a policy is not enough if it has lapsed or the dates don't cover the work being drawn down. Check the dates on the schedule, not just the policy name.
Stage 1: Foundations
Foundation / sub-floor complete
-
Stage payment certificate (engineer/architect signed)
Signed certificate for this construction stage.
-
Photos of poured foundation and sub-floor
Clear photos showing completed foundation/sub-floor work.
-
Material invoices for the period
Invoices for materials used in this stage.
-
Labour / contractor invoices
Contractor invoices if separate from materials.
-
Site insurance on file
Check that the policy dates on your schedule cover this stage, not just that a policy exists.
-
BCAR commencement notice acknowledged
Commencement / BCAR notices as applicable.
Stage 2: Walls and roof
Walls and roof on (wallplate level)
-
Stage payment certificate
Signed certificate for walls/roof stage.
-
Photos of completed walls and roof structure
Shell photographs lenders typically request.
-
Material invoices for blockwork, timber, roofing
Materials invoices for structural envelope.
-
Labour / contractor invoices
Labour invoices where separate.
-
Site insurance on file
Check that the policy dates on your schedule cover this stage, not just that a policy exists.
Stage 3: First fix
First fix (plastered, plumbed, wired)
-
Stage payment certificate
Signed certificate for first-fix stage.
-
Photos showing first-fix electrical, plumbing, plastering
Photos demonstrating installed services and plastering.
-
Material invoices for the period
Materials for first-fix trades.
-
Electrical design / plan (PlotPacer export accepted)
Design drawings if your lender expects them. May not apply if your lender does not require a formal electrical layout.
-
Site insurance on file
Check that the policy dates on your schedule cover this stage, not just that a policy exists.
Stage 4: Second fix
Second fix complete
-
Stage payment certificate
Signed certificate for second-fix stage.
-
Photos of fitted kitchens, sanitaryware, fittings
Interior completion-level photographs.
-
Material invoices for the period
Materials for kitchens, bathrooms, finishes.
-
Site insurance on file
Check that the policy dates on your schedule cover this stage, not just that a policy exists.
Stage 5: Completion
Completion / final drawdown
-
Final stage payment certificate
Final signed stage certificate.
-
Photos of finished interior and exterior
Completion photographs.
-
BCAR Certificate of Compliance on Completion
Completion BCAR documentation.
-
BER (Building Energy Rating) certificate
Final BER certificate.
-
Snag list signed off / resolved
Snagging cleared if applicable.
-
Final invoices for outstanding work
Outstanding trade invoices.
-
Insurance on file through handover
Check that the policy dates on your schedule cover this stage, not just that a policy exists.
Who usually supplies what
Roles vary by build. Your lender, broker or solicitor can confirm who signs what for your case.
| Evidence | Usually from |
|---|---|
| Stage payment certificate | Your engineer or architect |
| Material invoices | Your suppliers and builders' merchant |
| Labour invoices | Your builder or each trade |
| Progress photos | You, from site |
| Site insurance | Your insurer or broker |
| Commencement and completion (BCAR) documents | Your assigned certifier, engineer or architect |
| BER certificate | Your BER assessor |
| The drawdown request itself | Usually your broker or solicitor, to the lender |
This checklist is based on common Irish self-build lender practice and was last reviewed on 2026-07-10. It is a preparation aid only. It is not mortgage, financial, legal, planning or building-control advice, and it does not confirm approval or guarantee a drawdown. Requirements vary by lender and by case. Confirm what is required with your lender or broker and, where relevant, your engineer, architect, assigned certifier or solicitor.